Williams Construction Services Performs Biggest Lift of Transform I-66 Project

WATCH: Williams Construction Services and Williams Steel Erection Co., Inc.’s Rigging Division work together to place a 250 ton box girder above I-66 East.

On April 20th, 2022, the team at Williams Construction Services and Williams Steel Erection Co., Inc. performed the largest girder lift of the Transform 66 Outside the Beltway Project to date. Using three cranes and a Goldhofer SPMT Trailer, the 250 ton girder was moved into the highway and lifted into position during a five-hour full closure of I-66 East at the Route 28 interchange.

The carefully planned and coordinated operation presented many unique challenges, first and foremost the size of the girder. At 13 feet tall and 139 feet long, it is the tallest box girder of the project and the second longest. Because three cranes were required for the pick, keeping it level through constant communication between the operators was critical. The final location of the girder was also directly under a power line, which had to be shut down for the lift.

After the box girder was assembled next to the highway over the course of weeks, one end of the girder was placed on Williams Steel Erection Co., Inc.’s Goldhofer heavy haul trailer, while the other was lifted by a Link-Belt 200 ton crawler crane so the trailer could rotate it into the closed roadway. Once in position, the 200 ton was joined by a Link-Belt 300 ton truck crane and Liebherr 300 ton hydraulic crane. Working together, the three Williams Construction Services cranes lifted the girder into position above the highway to be secured by erector Webber before the highway reopened.

“Transform 66 Outside the Beltway” is a design-build project with VDOT, I-66 Express Mobility Partners, and general contractor FAM Construction. Construction began in 2017 to add express lanes to a 22.5-mile stretch of I-66 from I-495 in Falls Church to Route 29 in Gainesville. The project is scheduled to be completed in 2022.

I-66 Outside the Beltway Uses Nine Williams Construction Services Cranes

Williams Construction Services’ 300-ton LinkBelt and 200-ton LinkBelt lift a precast girder over I-66 East for the new Gainesville Park and Ride exit.
Sound Walls between Jermantown and Waples Mill Rds

As the Transform 66 Outside the Beltway project continues, Williams Construction Services is providing equipment rentals to multiple customers working on various projects along the highway. On January 27, 2021, nine different WCS cranes performed work for three different customers from 7:00 AM on Wednesday to 5:00 AM the following day.

The day began at the intersection of I-66 and I-495, where a 40-ton Terex worked with FAM to install rebar on new piers for eastbound express lane exits. Just down I-66 West from there, a 20-ton National and 35-ton Lorain installed sound walls for Webber at Gallows Road and Cedar Lane.

Rebar at Route 50 West

Continuing down I-66 West, WCS’s 125-ton Krupp was installing sound walls for Webber on the eastbound side of the highway between Jermantown Road and Waples Mill Road. WCS also provided Webber with a 100-ton LinkBelt to complete rebar installation on a new pier for the Route 50 West overpass.

After working five cranes during the day, four cranes were used for night lifts that required lane closures. At Route 50, WCS’s Liebherr 330-ton 1300 was used by Webber to lift precast girders for the new Route 50 East overpass. I-66 westbound lane closures were required for the girder delivery, and a 55-ton Terex assisted with unloading.

Precast Girders at Route 50 East

In Gainesville, a 300-ton and 200-ton LinkBelt teamed up with Indus to lift precast girders over I-66 East for a new exit into the Gainesville Park and Ride facility (see video). The size of the girders required each to be picked by two cranes and placed on the piers during overnight lane closures of I-66 East.

At the end of the 22-hour stretch, Williams Construction Services’ cranes and operators had worked upwards of 75 hours on I-66 at seven different locations. WCS has rented cranes to FAM, Webber, Indus, and other contractors throughout this project, and continues to work on bridge, pier, and sound wall installation at numerous locations along the project route.

“Transform 66 Outside the Beltway” is a design-build project with VDOT, I-66 Express Mobility Partners, and general contractor FAM. Construction began in 2017 to add express lanes to a 22.5-mile stretch of I-66 from I-495 in Falls Church to Route 29 in Gainesville. The project is scheduled to be completed in 2022.

Williams Cranes Help Transform I-66

This summer Williams Construction Services provided 13 cranes to erect girders on 8 bridges as part of VDOT’s and I-66 Express Mobility Partner’s “Transform 66 Outside the Beltway” project. The design-build project with general contractor FAM Construction began in 2017 to add express lanes to a 22.5-mile stretch of I-66 from I-495 in Falls Church to Route 29 in Gainesville.

In the summer of 2020, work began in earnest on replacing many of the bridges that run over the interstate. From Memorial Day to Labor Day, the WMATA Orange Line shut down, which allowed a small window for bridge work to be completed. During the maintenance shutdown, Williams Construction Services provided cranes and operators to erect bridge girders for the new spans of Cedar Lane, Gallows Road, and a new off ramp connecting I-66 Eastbound to I-495. Beyond the Orange Line, Williams Construction Services worked on Waples Mill Road, Poplar Tree Road, and Route 50 Westbound, and also widened I-66 over Cub Run and Bull Run.

Each bridge presents its own unique challenges, and requires a diverse fleet of cranes. Williams Construction Services used its 300 ton Link Belt, 210 ton Link Belt, 135 ton Grove, and 135 ton Link Belt during the execution of this project, and continues to work with FAM Construction on the remaining bridges over I-66. The “Transform 66 Outside the Beltway” project is scheduled to be completed in 2022.

See our cranes at work throughout the summer

Williams Steel Wins 2019 SEAA Project of the Year

Ballston Quarter Pedestrian Bridge

Williams Steel Erection Co., Inc. has once again won Project of the Year, this time for its work on the Ballston Quarter Pedestrian Walkway in Arlington, VA. This award was won in the Class II category.

The Project of the Year award, given by the Steel Erectors Association of America (SEAA), recognizes steel erection projects that “demonstrate complexity, unusual conditions, issues, and barriers requiring special management team action or performance.” Williams Steel won the Class III Project of the Year award in 2018 for its work on the Dulles Corridor Metrorail Project – Phase 2.

The company’s work on this project required problem solving a challenging, high-profile project involving complex steel framing and challenging site conditions. You can read more about this process here.

The awards ceremony, previously scheduled to be held at the 48th Annual SEAA National Convention and Trade Show in Charleston, SC, was cancelled due to COVID-19 restrictions. The project will be featured in SEAA’s Connector trade magazine later this year.

Community Interest in Ballston Bridge

It is great to see lots of interest from the community on the recently erected Ballston Quarter pedestrian bridge completed by Williams Steel Erection Co., Inc. The Williams Steel team is honored to be able to use our expertise to enhance our community and the whole mid-Atlantic region. This post contains some highlights of the operation from around the internet.

Ballston Quarter Pedestrian Bridge

Note: Links are to external sites not operated by Williams Industries, Inc.  Williams Industries, Inc. does not accept any responsibility for the content or views expressed on external sites.


The Ballston Quarter pedestrian bridge was moved into place on Saturday, Feb. 16, spanning Wilson Boulevard.


Workers are installing a new and improved pedestrian bridge over Wilson Blvd in Ballston this weekend, but that will mean some major road closures.


Another Bridge at Loudoun Gateway

Williams Steel Erection Co., Inc. and Williams Construction Services have done it again with the erection of a pedestrian bridge connecting the new Loudoun Gateway Station on the second phase of the Washington Metro’s Silver Line to a new parking garage being built by Loudoun County to service the station.

This 175 ft long, 100 ton bridge was assembled on the ground in two pieces and set in place using Williams Construction Services 300 Ton capacity truck crane.

To successfully complete this project, Williams Steel drew on their extensive experience building pedestrian bridges on 5 of the stations that make up the second phase of the Silver Line for which they won a 2019 Washington Building Congress Craftsmanship Award. The Loudoun Gateway Station can be seen in the background of the photo above.

The tight placement and size of this bridge provided unique conditions which Williams Steel overcame by building the bridge in two sections utilizing a custom engineered shoring solution to support the bridge during final placement. It is this type of carefully planned operation that Williams Steel Erection and Williams Construction Services specialize in.

Check out more pictures of this operation below.

Connecting Arlington

The Ballston Quarter pedestrian bridge crossing Wilson Boulevard in Arlington, Virginia has been a community landmark for many years. When the owner decided to replace the bridge they wanted to create an iconic structure that would set it apart and had a daring architectural design prepared. Then they had to build it.

This is where Williams Steel Erection Co., Inc. comes in. The complex shape, large size, and location over a busy street in downtown Arlington are just some of the challenges that had to be overcome to build the structure. To make it happen, Williams Steel used innovative “accelerated bridge construction” methods that it has become known for.

First, the 145 ft long, 100 ton bridge was completely assembled about a quarter of a mile from the final location in Mosaic Park. The bridge was fabricated by Crystal Steel Fabricators in Memphis, Tennessee and shipped to Virginia in large, truck-sized pieces.

Bridge during assembly in Mosaic Park.
Fully assembled bridge.

Next, the bridge was loaded onto, Williams Steel’s Goldhofer heavy haul trailer pulled by our Oshkosh M1040 prime mover and moved from the park to the final location. This operation involved significant coordination to close streets, move traffic lights and signs, and keep the public safe.

Diagram of bridge transportation path through Arlington.
The Goldhofer heavy haul rig transporting the bridge.

Finally, the bridge was hoisted into place using a 600 Ton capacity crane and set down on the piers.

Bridge being hoisted into place.

Building the bridge structure using this method saved weeks to months of road closures on Wilson Boulevard and eliminated many of the safety risks associated with a partially completed structure being built over a road. When done properly by experienced professionals, this type of operation is much safer and simpler than traditional methods of construction over roadways.

The team at Williams Steel Erection Co., Inc. provides the resources and experience to complete this and other projects of similar complexity and standing. We are honored to be able to use these abilities to provide services that enhance our community and communities throughout the mid-Atlantic region.

Pedestrian Bridge Erection for Silver Line Extension

Williams Steel Erection Co., Inc. is assembling and erecting 32 pedestrian bridges for Phase 2 of the Dulles Corridor Metrorail Silver Line Extension project.  The bridges will connect the 5 at-grade stations in the median of the Dulles Toll Road and Dulles  Greenway to the wayside parking areas.  Below are pictures from August 21st and 23rd setting 2 spans at the new Herndon Station.  Check back soon for more updates on this project.

1 2